High Line Division S.L. performs the construction of 7 km of 13,8 kV distribution line from Qataban Substation to North East Sunah/Hemiar Junction in 85 Days including demobilization with Zero incident, accident, environmental or material damage reported.
Works starts the 1st July 2014 with Crew arrival to Petromasila Installations at Hadramawt, CPF, Masila Field.
Starting with Poles preparation, two piece poles assembly using Hydraulic Pump for assembly and insulators, guy wires and earth wire supports drilling works...
We proceed with the erection of Poles.
Stringing and Sagging conductors have been performed as per international standards, using Hydraulic tensioner and hydraulic conductors breaking equipment, manufactured for this purpose by Tesmec.
Then, after sagging process we proceed with armour rods and general hardware & fittings installation...
Testing & Commissioning works with final Tie In was performed following the international standards and protocols apply to the industry after a successful insulator resistance test.
Project was completed achieving all established objectives related to Quality, Safety and Environment Protection, and as usual in High Line Division exceeding Client expectations as shown the Completion Certificate provided by Petromasila.